Damping force adjustment
Break-inCushion lever removal and installation
Removal
Remove the right side cowling and side frame covers. Refer to “exterior
parts removal and installation” in section 9d .
Support the motorcycle with a jack to relieve load on
the cushion levers.
Remove the left muffler and muffler chamber heat guard no. 2. Refer to
...
Pair system inspection
Inspect pair system
every 12 000 km (7 500 miles, 24 months)
Inspect the pair (air supply) system periodically. Refer to “pair system
inspection” in section 1b .
Throttle valve synchronization
Inspect throttle valve synchronization
initially at 1 000 km (600 miles, 2 months) (e-33 only)
and ...
Throtile cable play
This motorcycle has a twin throttle
cable system. Cable A is for pulling
cable and cable B is for
returning.
To adjust the cable play:
Loosen the lock nut 1.
Turn the adjuster 2 so that the
throttle grip has 2.0 - 4.0 Mm
(0.08- 0.16 In) play.Tighten the lock nut 1.
...