Special tools and equipment
General descriptionIsc valve preset and opening initialization
When removing or replacing the isc valve, set the isc
valve to the following procedures:
turn the ignition switch on.
Set up the sds tool. (Refer to the sds operation
manual for further details.)
Click the “active control”.
Click the “isc learned value reset” (1) ...
Drive chain cleaning and lubricating
Clean and lubricate drive chain
every 1 000 km (600 miles)
Clean and lubricate the drive chain in the following
procedures:
clean the drive chain with kerosine. If the drive chain
tends to rust quickly, the intervals must be
shortened.
Caution
do not use trichloroethyle ...
Rear shock absorber adjustment
After installing the rear suspension, adjust the spring
pre-load and damping force as follows:
Spring pre-load adjustment
The set length 179.3 Mm (7.06 In) provides the
maximum spring pre-load.
The set length 189.3 Mm (7.45 In) provides the
minimum spring pre-load.
Std position
184.3 ...